The Court dismissed the originating application and ordered Steller Developments to pay Mr Smedley's costs incurred in relation to the originating application on a party and party basis. It also ordered Atlas to be jointly and severally liable with Steller Developments for those costs. Separate fixed costs orders were made in favour of Mr Cirelli and Mr Vines, and the Court made orders about release of security for costs, subject to a 42-day stay pending appeal.
But the Court refused the additional costs orders sought by Mr Smedley.
On the cross-claim costs issue, the Court said the authorities relied on by Mr Smedley did not fit the actual procedural position. Those authorities commonly deal with a successful defendant who brought a third-party claim or cross-claim and then seeks to recover related costs. Here, Mr Smedley was different. He was a successful respondent on the principal claim, but he did not bring the cross-claim. He was defending a cross-claim brought by Mr Vines. He also had not been ordered to pay anyone else's costs on that cross-claim.
The Court accepted that the principal claim was the catalyst for the cross-claim. But it said causation alone was not enough to shift the burden of costs. It also rejected the suggestion that it was obvious the cross-claim would simply stand or fall with the principal claim. If the principal claim had succeeded, the cross-claim still required determination of issues unique to the Retirement Agreement. The Court also noted there was no reason to believe Steller Developments knew of the Retirement Agreement when it commenced the principal claim. For those reasons, the Court was not persuaded that Steller Developments should pay Mr Smedley's own costs of defending the cross-claim.
On indemnity costs, the Court rejected Mr Smedley's argument that the construction case had been brought in wilful disregard of the law. The Court accepted that, with hindsight, some aspects of the construction case were weak, but said mere weakness does not justify indemnity costs. The Court also rejected the argument that the rectification case had been brought in wilful disregard of the facts. It described that case as weak, and considerably weaker than the construction case, but still held that indemnity costs were not warranted. The Court also noted that Mr Smedley had not tendered correspondence showing that these alleged defects had been clearly put to Steller Developments before or during the proceeding.
On the funder issue, Atlas had indicated it would submit to an order making it jointly and severally liable for Mr Smedley's costs of the principal claim on a party and party basis, but objected to any broader order. Because the Court refused cross-claim costs and indemnity costs, the narrower order was sufficient. So Atlas was liable only for the ordinary costs of the principal claim, not for indemnity costs and not for cross-claim costs.