This Federal Court case started with a residential building project in Queensland, but the issues are familiar across many industries. A customer engaged a supplier under a staged-payment contract. The work did not finish. The customer later said the supplier had delayed performance, caused finance problems and engaged in misleading, deceptive and unconscionable conduct. The supplier said the real problem was non-payment of a progress claim and relied on the contract’s suspension and termination machinery.
Yu Wang contracted with Creation Homes QLD Pty Ltd to build a home in Coomera. The contract was signed on 2 February 2016. Construction did not begin immediately. The timing of land registration, finance and building approval all became important. Work eventually started in April 2018, the base stage was completed and paid, and the frame stage was then completed. On 30 May 2018 Creation issued a frame stage progress claim for $51,800. Ms Wang did not pay it. She said her construction loan had expired because of the delay and that she had reapplied for finance. Creation suspended work, later issued a notice to remedy, and then terminated the contract in January 2020.
Ms Wang commenced proceedings in December 2024. She sought damages under the Australian Consumer Law and also advanced a contract case. Creation defended the claim and cross-claimed for the unpaid frame stage amount and contractual damages. The court dismissed Ms Wang’s application and gave judgment for Creation on the cross-claim.