Selected cases

CTH · [2026] FCA 536

Priority

Narayan, in the matter of Elexsys Energy Pty Ltd (Receivers and Managers Appointed) [2026] FCA 536

After receivers were appointed to Elexsys Energy, a dispute arose over eight CATL batteries claimed by the secured creditor, a director and a supplier. The Federal Court held that the batteries were owned by Elexsys Energy, had not been validly transferred to the director, and were not owned by the supplier. Marketlend was therefore entitled to seize them under the PPSA. The case is a practical reminder about security drafting, retention of title, PPSR compliance and the need for admissible business records.

CTH1 May 2026

These are plain-English explainers, not legal advice. They are a good starting point, but check the linked official source before you rely on a specific section, and get advice for your situation.

Talk to a lawyer

Decision snapshot

Facts

The dispute

The proceeding was brought after receivers were appointed on 23 October 2023 to Elexsys Energy Pty Ltd and Elexsys R&D Pty Ltd by a secured creditor, Marketlend. The central dispute concerned eight large batteries described in the orders as “Battery = CATL 233kW/233Kwh”. Marketlend and the receivers said the batteries were assets of Elexsys Energy and were therefore caught by Marketlend’s security. The defendants denied that. Mr Holcombe, a director of Elexsys Energy, claimed the batteries were owned by him or alternatively by Ocean Energy Pty Ltd. Ocean Energy was joined because it said it had supplied the batteries under a retention of title arrangement and remained the true owner. The judgment also records an important practical development. When the proceeding started, the receivers sought to restrain assets from being removed from the Enoggera property where the companies had conducted business. By then, Mr Holcombe had taken possession of the batteries. An interlocutory dispute was resolved by an undertaking that he would retain, preserve and not deal with or dispose of the assets, including the batteries, without seven business days' written notice to the receivers or further court order. The court said it appeared that after giving that undertaking, he permitted Ocean Energy to take possession of some or all of the batteries without notice. The case was also shaped by repeated procedural defaults. The defendants were given multiple extensions to file defences, evidence and submissions, but largely failed to comply. At the final hearing, the court admitted only limited defence material, including a BESS supply agreement and a bundle of invoices, and rejected much of the rest because it was unsupported, hearsay, unsigned, undated, or appeared prepared for the litigation without proper proof.

Issue

The legal question

The court had to decide whether Marketlend, as secured creditor, could enforce security over eight CATL batteries after receivers were appointed to Elexsys Energy and Elexsys R&D. That required the court to determine who owned the batteries, whether the general security deeds effectively charged Elexsys Energy's present and after-acquired property despite awkward drafting, and whether the batteries could be seized under section 123 of the PPSA. The case also raised retention of title and perfection issues because Ocean Energy claimed to have supplied the batteries on terms that preserved its ownership.

Outcome

Decision

The plaintiffs succeeded. The court declared that the eight CATL batteries were owned by Elexsys Energy, were not validly transferred to Mr Holcombe, and were not otherwise owned by Ocean Energy. It further declared that Marketlend was entitled, under section 123 of the Personal Property Securities Act 2009 (Cth), to seize the batteries in accordance with its rights. The court restrained Mr Holcombe and Ocean Energy from preventing Marketlend and its officers, employees and agents from seizing the batteries, and ordered the defendants to pay the plaintiffs' costs. The judgment also accepted unchallenged evidence of unpaid amounts under the trade credit arrangements supporting enforcement.

Practical impact

Commercial note

Read this case as a document-management and asset-control warning. If your business buys goods on supplier terms, borrows against present and after-acquired property, or stores assets with directors, related entities or third parties, your contracts need to line up before a dispute starts. The court was prepared to give awkwardly drafted security clauses a businesslike interpretation where the commercial purpose was clear, so poor drafting did not save the defendants. At the same time, a supplier could not simply rely on saying there was retention of title and expect that to defeat the lender. The judgment’s catchwords show that perfection of a security interest was part of the analysis, which underlines the importance of PPSA registration where required. Businesses should keep signed supply agreements, invoices, delivery records, payment records and PPSR registrations in a form that can actually be proved. If insolvency or enforcement begins, do not move disputed assets or attempt informal transfers without urgent legal advice.

The story

This Federal Court case arose out of a receivership, but the commercial setting is broader than insolvency alone. Elexsys Energy had entered into trade credit arrangements with Marketlend, and those arrangements were supported by general security deeds. After receivers were appointed, a dispute emerged over eight large CATL batteries. The receivers and Marketlend said the batteries belonged to Elexsys Energy and were therefore subject to Marketlend's security. Mr Holcombe and Ocean Energy said that was wrong.

The competing claims were commercially significant. Mr Holcombe was a director of Elexsys Energy and claimed the batteries were owned by him or, alternatively, by Ocean Energy. Ocean Energy said it had supplied the batteries on a retention of title basis, meaning ownership had not passed because payment had not been completed. That turned the case into a practical contest between three familiar positions in distressed businesses: a lender relying on broad security, a supplier relying on title retention, and insiders asserting that the company never owned the goods at all.

How the dispute developed

The judgment records that when the proceeding began, the receivers sought orders to stop assets being removed from the Enoggera property where Elexsys Energy and Elexsys R&D had conducted business. By that point, Mr Holcombe had already taken possession of the CATL batteries. The immediate interlocutory fight was resolved by an undertaking given on 6 December 2023. Under that undertaking, Mr Holcombe agreed to retain, preserve and not otherwise deal with or dispose of various assets, including the batteries, without seven business days' written notice to the receivers or until further court order.

The court then noted an important factual development. After giving the undertaking, Mr Holcombe appears to have permitted Ocean Energy to take possession of some or all of the batteries without giving notice to the plaintiffs. The plaintiffs had raised a claim that this breached the undertaking, but that issue was not pressed to final determination. The final hearing instead focused on the core commercial questions about ownership, security and seizure.

The procedural history was unusually important. The defendants were repeatedly ordered to file defences, evidence and submissions, and repeatedly failed to comply. Extensions were granted across 2024 and 2025, but the pattern of non-compliance continued. By the time of the final hearing, the defendants had not filed proper evidence and sought to rely on late material sent to chambers the day before the hearing. The court allowed reliance on an updated defence, but admitted only some of the documents the defendants wanted to use.

Quick checklist

0/5

What the court had to decide

The court identified the issues directly. First, whether Marketlend was entitled to enforce the security granted in its favour over Elexsys Energy's assets, including the batteries. Second, whether the batteries were owned by Elexsys Energy, Ocean Energy or Mr Holcombe. Third, if the batteries remained owned by Ocean Energy or had been validly transferred to Mr Holcombe, whether they were still charged in favour of Marketlend and remained subject to its security under sections 19 and 32 of the PPSA, and whether they could be seized under section 123. Fourth, whether the court should order seizure or delivery up.

That structure matters because the case was not simply about title in the ordinary sale of goods sense. It also involved PPSA concepts about attachment, security interests, perfection and enforcement. The catchwords confirm that the court considered the effect of a retention of title clause and the effect of perfection of a security interest. Even though the full reasoning on those points is not fully reproduced in the text reviewed here, the issues show how quickly a supply dispute can become a PPSA enforcement dispute.

The court also had to interpret awkwardly drafted charging clauses in the general security deeds. That was a real issue, not a technical side point. If the clauses failed, Marketlend's enforcement case could have been undermined. The judgment therefore deals with how a court approaches clumsy drafting in a commercial security document.

The security documents and the court's reasoning

The judgment sets out part of the finance structure in detail. Marketlend had entered into a series of trade credit agreements with Elexsys Energy over time. The court said there were eight separate finance facilities between about 23 November 2017 and about 16 November 2021, although the plaintiffs ultimately relied on three of them. Those facilities were supported by general security deeds incorporated into the trade credit documents.

The first deed, linked to a 27 November 2017 trade credit agreement, used wording that the court described as inelegant and awkward. It said the account holder charged all its present and after-acquired right, title and interest “in the Seller” to Marketlend. Read literally, that wording was commercially odd because the seller was Marketlend itself. The court approached the clause using orthodox principles of commercial interpretation. It referred to High Court authority confirming that a commercial contract should be read in the way a reasonable businessperson would understand it, by reference to text, context and purpose, while recognising that commerciality does not justify rewriting the bargain.

Applying those principles, the court held that the purpose of the deed was plainly to provide security for Elexsys Energy's obligations under the trade credit agreement. In that context, the word “in” in the charging clause was read as meaning “in favour of”, so the clause operated as a charge in favour of and to Marketlend over Elexsys Energy's present and after-acquired property.

The second and third deeds had a different but equally awkward problem. Their wording suggested that Elexsys Energy charged all of its present and after-acquired right, title and interest “in the Account Holder” to Marketlend. Again, a literal reading would have produced an odd result, as if the company were charging rights in itself rather than in property it held. The court held that, in context, “in” should be read as meaning “held by”. On that reading, the deeds granted a charge over the present and after-acquired right, title and interest held by Elexsys Energy, which was commercially sensible and consistent with the evident purpose of the documents.

The court also accepted unchallenged evidence that there were unpaid invoices under the trade credit agreements. For TCA1, the judgment records unpaid invoices totalling $113,604.27 inclusive of late fees and $111,291.20 exclusive of late fees. For TCA2, the extract records unpaid invoices totalling $218,229.65 inclusive of late fees before the text cuts off. The court said this unchallenged evidence supported the conclusion that Elexsys Energy was indebted to Marketlend in a way that entitled Marketlend to exercise the charge granted in its favour.

For business readers, the key point is not that drafting quality does not matter. It does. The point is that a court may still uphold a security document if the text, context and purpose make the intended commercial operation sufficiently clear. But relying on a court to rescue poor drafting is expensive and risky. It is far better to ensure the charging language is clear when the documents are signed.

Ownership, retention of title and PPSA enforcement

The final orders are clear about the result. The court declared that the eight CATL batteries were owned by Elexsys Energy. It also declared that they were not validly transferred to Mr Holcombe and were not otherwise owned by Ocean Energy. On that footing, the court further declared that Marketlend was entitled, under section 123 of the PPSA, to seize the batteries in accordance with its rights.

That outcome means the competing ownership positions failed. Mr Holcombe's personal claim did not succeed. Ocean Energy's claim to ownership also failed. The court then restrained Mr Holcombe and Ocean Energy from preventing Marketlend, and its officers, employees and agents, from seizing the batteries. Costs were ordered against the defendants.

The catchwords show that the court considered the effect of a retention of title clause and the effect of perfection of a security interest. That is especially important for suppliers. In many commercial arrangements, a supplier assumes that if its invoice or supply agreement says title is retained until payment, that will be enough to protect the goods if the buyer becomes insolvent. This case is a reminder that the analysis can be more complicated. Once the PPSA is engaged, the legal character of the arrangement, the existence and perfection of any security interest, and the interaction with a lender's security can all matter.

Because the text reviewed here is truncated, it is sensible not to overstate the court's full reasoning on the retention of title and perfection issues. But the practical message is still strong. If your business supplies valuable goods on credit and expects to rely on retention of title, you should not assume that invoice wording alone will carry the day in a later insolvency dispute. The supply agreement, invoice terms, delivery records, payment records and PPSR position should all be checked together.

Quick checklist

0/5

Documents and conduct in court

A major part of the judgment concerns evidence and procedure. The defendants tried to rely on a range of documents at the last minute, including balance sheets, profit and loss statements, Xero material, reconciliations, file notes, email correspondence, and draft affidavits. The court rejected much of this material. Some documents purported to be business records, but there were anomalies on their face, some appeared annotated or compiled from other records without explanation, and there was no affidavit or witness evidence properly proving how they had been created. Mr Holcombe was unable to establish their provenance and said he assumed they came from Xero, but he had not retrieved or produced them himself.

The court also rejected without prejudice correspondence, a submission-style document tendered as evidence, draft affidavits that were unsigned or undated, and file notes that were prima facie hearsay. The judge was explicit that accepting belated evidence of that kind would create a trial by ambush after the defendants had already been given ample opportunity to present their case. Only a limited number of documents were admitted, including a BESS Supply Agreement dated 6 April 2021 between Elexsys Energy and Ocean Energy, and a bundle of invoices that the defendants relied on to show retention of title notations.

This part of the case is highly practical for business owners. Commercial disputes are often decided less by broad assertions than by whether the records can be proved through a competent witness. A spreadsheet, accounting export or internal note may look persuasive inside the business, but if no one can explain where it came from, when it was created, whether it was altered, and how it fits with the underlying transaction, a court may give it little or no weight.

Quick checklist

0/5

How businesses should read it

If you are a borrower, this case is a reminder that a general security in favour of a lender can extend broadly across present and after-acquired property, and that a court may interpret the document in a commercially sensible way even if the drafting is clumsy. If you are a supplier, it is a reminder that retention of title language should be treated as part of a larger PPSA compliance exercise, not as a complete answer by itself. If you are a director or related party, it is a reminder that personal claims to company assets, or alleged transfers out of the company, will be closely examined once insolvency or receivership begins.

For founders, SMEs and operational managers, the most useful question is simple: could your business prove today who owns each major item of stock or equipment, who has possession, whether a lender has security over it, whether a supplier has retained title, and whether any PPSR registration has been made? If the answer is uncertain, the risk is not just legal complexity. It can mean losing access to essential assets, being unable to resist enforcement, or being left with a claim that cannot be proved.

This case should also prompt a practical review of how documents are stored and matched. Supply agreements, invoices, purchase orders, delivery dockets, payment records, board approvals and security documents should tell the same story. If they do not, the inconsistency may only become obvious when a receiver, lender or court starts asking questions.

Source notes

This page summarises the Federal Court decision in Narayan, in the matter of Elexsys Energy Pty Ltd (Receivers and Managers Appointed) [2026] FCA 536, judgment of Shariff J dated 1 May 2026. The published material reviewed for this page included the formal orders, the introduction, procedural history, and part of the court's analysis of the trade credit agreements and general security deeds.

The text reviewed did not include the whole judgment. As a result, the result and several key reasoning steps can be stated confidently, but some detail on the court's full retention of title and perfection analysis is not set out here in full.

How Sprintlaw can help