Selected cases

New South Wales Court of Appeal · [2026] NSWCA 175

Reece Australia Pty Ltd v Alamdo Holdings Pty Ltd

The lease remained on foot and the landlord's $1,552,310.35 judgment was upheld.

New South Wales Court of Appeal27 Aug 2026

Plain-English explainers, not legal advice. Use the linked official source for section-level detail, and get advice for your situation.

Get legal help

Start here

Quick read

  • A deadline or termination right in a lease is not a free option.
  • A commercial tenant could not terminate a ten-year warehouse lease after an occupation certificate deadline was missed because its own failure to provide a proper...

Use this to check

  • The lease required the tenant to give council all information needed to process the application expeditiously
  • A general BCA report was not enough where council needed a clause-by-clause assessment of the fit-out and existing building
  • An ambiguous regulator request should be clarified promptly rather than interpreted in the narrowest convenient way

Decision snapshot

  1. What happened

    • Reece Australia and Alamdo Holdings signed a ten-year lease over a Castle Hill warehouse on 23 December 2022.
    • Reece planned a fit-out and change of use for wholesale trade.
    • The lease required Reece to provide the plans, statements and information the council required to process its development application expeditiously.
    • It also allowed either party to terminate if an occupation certificate was not obtained by 23 June 2023.
  2. What the court had to decide

    • The appeal asked whether Reece had breached its obligation to provide the council information needed for an expeditious application, whether the landlord's outstanding fire safety order caused the delay instead, and whether there was a substantial chance that an occupation certificate would have been obtained by the contractual deadline if Reece had...
  3. What the court decided

    • The Court of Appeal dismissed Reece's appeal.
    • Council's request required a proper BCA compliance report addressing the proposed fit-out and the existing building.
    • If Reece considered the request ambiguous, its contractual duty required it to seek clarification.

Practical impact

Practical read

  • A deadline or termination right in a lease is not a free option.
  • A party may lose the right to rely on it when its own failure helps cause the condition to fail.
  • Fit-out approvals need a documented owner, clear consultant instructions and a timetable tied to the lease, not just the council's outer response periods.

Useful next steps

  • The lease required the tenant to give council all information needed to process the application expeditiously
  • A general BCA report was not enough where council needed a clause-by-clause assessment of the fit-out and existing building
  • An ambiguous regulator request should be clarified promptly rather than interpreted in the narrowest convenient way
  • A party may be unable to use a termination condition when its own breach materially contributed to the missed condition
  • Planning, construction and occupation-certificate dates should be managed as contractual deadlines

The lease tied the fit-out to a six-month deadline

Reece leased a warehouse unit at Castle Hill for ten years, with options to renew. It planned to change the use from an indoor trampoline facility to wholesale trade and complete a fit-out.

Article 29 of the lease split responsibility for the approval process. Reece had to lodge the development application and provide all plans, statements and other information required for council to process it expeditiously. If an occupation certificate was not obtained by 23 June 2023, either party had an express right to terminate.

Council asked for a BCA report before the lease was signed

On 15 December 2022, Reece's planning consultant called council to ask what the development application needed. Council said a BCA report for the fit-out was required.

A report was produced quickly and lodged with the application. It said that no major concerns had been identified, but it did not assess the relevant Building Code provisions clause by clause across the fit-out and the existing building. That detail mattered because council needed enough information to assess an application involving an existing building.

The Court said that if the words 'BCA report for a fit out' seemed unclear, Reece was obliged to clarify the requirement. It could not rely on ambiguity while also promising the landlord that it would provide what council needed expeditiously.

Later information requests did not reset the lease timetable

Council later issued requests for further information. Reece argued that the formal response periods meant there was not enough time to obtain consent and complete the fit-out before 23 June.

The Court rejected that approach. A regulator's maximum response period did not replace Reece's separate contractual obligation to act expeditiously. The trial evidence showed that other likely information requests were minor and could have been handled promptly or at the same time as other work.

Key points

  • Build the approval program backwards from the lease deadline
  • Give consultants the lease obligations as well as the planning brief
  • Clarify unclear council requests in writing
  • Track response dates that are commercially necessary, not only the regulator's maximum period
  • Run design, consultant and approval tasks in parallel where that is properly available

The existing fire safety order did not shift responsibility

The building was subject to an outstanding fire safety order. Reece knew about it shortly before signing and received assurances from the landlord about the remaining work. On appeal, Reece argued that the order and the landlord's position caused the delay.

The evidence did not establish that connection. Council had asked for the BCA report independently of the fire safety order. Nor was there evidence that council would refuse development consent until all work under the order was complete. The main delay followed the inadequate report and Reece's responses.

The case still shows why base-building compliance and tenant fit-out obligations should be separated clearly in the lease. But a landlord issue does not excuse a tenant from performing its own approval obligations.

The attempted exit left the lease and the debt in place

Reece purported to terminate on 27 June 2023, four days after the occupation-certificate deadline. Alamdo challenged the termination.

At trial, the Court declared that the termination was invalid and the ten-year lease remained on foot. It entered judgment for Alamdo for $1,552,310.35 in unpaid rent and outgoings. The Court of Appeal dismissed Reece's appeal and ordered it to pay the landlord's appeal costs.

The financial consequence is the clearest practical lesson. A disputed termination can leave a tenant exposed not only to fit-out costs and legal fees, but also to continuing rent and outgoings under the lease it thought it had ended.

Controls to put around a fit-out condition

Key points

  • Allocate each planning, building and landlord deliverable to a named person
  • Record which party is responsible for base-building work and which is responsible for the fit-out
  • Give consultants the contractual deadline and the standard of performance required by the lease
  • Require written confirmation of what council needs before lodging
  • Escalate missing or inadequate reports early enough to replace them
  • Take advice before exercising a termination right where your own performance may be disputed

Common questions

Did the lease contain an express termination right?

Yes. Either party could terminate if an occupation certificate was not obtained within six months of commencement, by 23 June 2023. The problem was that Reece's own breach materially contributed to the condition not being met.

Why was the first BCA report inadequate?

Council needed a report that assessed compliance clause by clause for both the proposed fit-out and the existing building. The first report did not provide that analysis, so council did not have the information needed for its assessment.

Was the landlord's fire safety order the cause of the delay?

The Court held that it was not. Council communicated the BCA-report requirement independently of the fire safety order. The evidence also did not show that the order prevented consent once an adequate report was provided.

What was the position after the appeal?

The appeal was dismissed. The declaration that Reece's termination was invalid and the lease remained on foot was undisturbed, as was the $1,552,310.35 judgment for unpaid rent and outgoings.

Related topics

How Sprintlaw can help

Update history

Case27 Aug 2026

Commercial tenant loses appeal over fit-out deadline

The New South Wales Court of Appeal held that a commercial tenant could not rely on an occupation-certificate termination condition after its own failure to provide a proper BCA report materially contributed to the missed deadline.